Below is a timeline guide to help you plan large projects.. If you would like more guidance or information, please contact us.

BPO/Prep Work

Weeks Needed

BPO/Prep Work

2 Weeks

CAD Files To Winwear

3 Weeks

Fabric Submittal/Approval

10 Weeks

Submittal Review & Final Approval

4 Weeks

Pocket Procurement

12 Weeks

Pocket Install

3 Weeks

Electrical Procurement

7 Weeks

Eletrical Install

2 Weeks

Measure & Order Shades

2 Weeks

Shade Production

7 Weeks

Freight

1 Week

Installation

4 Weeks

Commissioning

1 Week

Punch List

1 Week