Large Project Planning Guide
Below is a timeline guide to help you plan large projects.. If you would like more guidance or information, please contact us.
BPO/Prep Work
Weeks Needed
BPO/Prep Work
2 Weeks
CAD Files To Winwear
3 Weeks
Fabric Submittal/Approval
10 Weeks
Submittal Review & Final Approval
4 Weeks
Pocket Procurement
12 Weeks
Pocket Install
3 Weeks
Electrical Procurement
7 Weeks
Eletrical Install
2 Weeks
Measure & Order Shades
2 Weeks
Shade Production
7 Weeks
Freight
1 Week
Installation
4 Weeks
Commissioning
1 Week
Punch List
1 Week